Safety Decking for Steelframe builds
Bondeck recently completed this major safety decking project for one of the UK’s largest commercial developers. The build required a 2.8 metre high platform for the construction of a 800 square metre cut roof. Erected in only two days, the decking (a combination of our full-height and Lo-deck systems was installed in a fluid rolling programme to provide a working platform and leading edge protection for the carpenters installing the roof.
The client estimated the use of decking provided a fourteen day saving in the build programme (the alternative had been birdcage scaffold).
The system was fully braced and tensioned to ensure a stable lightweight working platform. Both the client and the carpentry sub-contractor, neither of whom had used the system before, declared themselves delighted with the result commenting that they “liked the simple solution the system brought to the project”.